Talisker Provides Ore Sorter Facility Update for the Bralorne Gold Project
Talisker Resources (TSX: TSK)
Provided an update on the continued advancement of its ore sorter facility at the Bralorne Gold Project.
Construction and engineering activities have continued to advance according to plan, with several major project milestones already completed and a number of critical work programs now entering the execution phase.
.

.
| Talisker Resources | TSX: TSK | |
| Stage | Development | |
| Metals | Gold | |
| Market cap | C$1626million @ C$0.60 | |
| Location | British Colombia | |
| Website | www.taliskerresources.com |
.
Talisker Provides Ore Sorter Facility Construction Update for the Bralorne Gold Project
November 18, 2026
TORONTO, Nov. 18, 2026 (GLOBE NEWSWIRE) — Talisker Resources Ltd. (“Talisker” or the “Company”) (TSX: TSK, OTCQX: TSKFF) is pleased to provide an update on the continued advancement of its ore sorter facility (“Sorting Facility”) at the Company’s 100% owned Bralorne Gold Project (“Bralorne”).
Construction and engineering activities have continued to advance according to plan, with several major project milestones already completed and a number of critical work programs now entering the execution phase.
.
Key Highlights:
- Initial operation of the Sorting Facility is targeted for Q2 2027, with full commissioning expected in July-August 2027.
- Electrical infrastructure is completed and targeted for commissioning by the end of November 2026, providing power for the future operation of the Sorting Facility.
- Phase 1 earthworks associated with the electrical infrastructure required to support the Sorting Facility were successfully completed in September.
- Phase 2 earthworks and concrete foundation construction is planned to commence late November 2026, following removal of legacy infrastructure.
- Factory Acceptance Testing (FAT) of the TOMRA XRT Sorter is scheduled for early December 2026, with the ore sorter expected to arrive in Canada in January 2027.
- Major long-lead equipment procurement is substantially complete, with the jaw crusher, cone crusher, vibrating screen plant received in Bralorne in October, conveyors, compressors, and buildings being delivered in phases starting December 2026.
- Construction and mechanical installation activities are planned throughout Q1 2027, supported by completion of detailed engineering and issuance of the remaining construction tender packages in December 2026.
.
Terry Harbort, President and CEO, stated,
“We are very pleased with the progress being made on the Sorting Facility.
.
“With key infrastructure completed, major equipment secured, and construction activities continuing to ramp up, the project remains on schedule for operational readiness in Q2 2027.
.
“This Sorting Facility represents an important milestone for Bralorne and will play a significant role in improving operational efficiency and supporting the Company’s long-term growth objectives.”
.
To read the full report please click HERE
+++++++
To view the latest share price and chart, please click HERE
To View Talisker Resources historical news, please click here
.
+++++++
City Investors Circle is based in the financial district in the City of London
We present interesting and exciting junior mining companies listed on the ASX and TSX stock exchanges to a group of city professionals, and private investors, all of whom are active investors with a mandate to invest in junior mining companies.
Our audience is selected and invited individually to ensure interest and relevance for the presenting company.
Meetings are non deal, small group, highly focused and engaged, with a lively Q and A to follow the main presentation.
We create awareness, and maintain interest in presenting companies by disseminating their future news to our entire investor group via email, social media, and our Monthly Review newsletter.
If you wish to present to our select group of active mining investors, please email andrew@city-investors-circle.com
.
=======
,
This website is not sponsored, we are truly independent, and will always remain so.
Companies featured here have either presented to the Circle in London, or have been selected because they are considered to have interesting projects, in good jurisdictions, run by an experienced management team.
All information used in the preparation of this communication has been compiled from publicly available sources that we believe to be accurate and reliable, however, we cannot, and do not, guarantee the accuracy or completeness of this.
These articles are for awareness and informational purposes only, and are not recommendations in any form. Always consult an investment professional.
.
Disclosure
At the time of writing the author holds shares in Talisker Resources
.
.