Calidus Warrawoona Gold Mine Record Production in February

Calidus Resources (ASX:CAI)

Provided an update on operations at its Warrawoona Gold Project in February 2023.

A total of 182,000 tonnes of ore at a reconciled grade of 0.89 g/t was processed with 5,005 ounces of gold recovered. This equates to 180 ounces per day or 66,000 ounces annualised. 

.

.

.

Calidus Resources

Calidus Resources Warrawoona mine

.

.

.

Calidus Resources ASX: CAI
Stage Production, exploration
Metals Gold, lithium
Market Cap A$105 m  @ A$0.24
Location Pilbara, Western Australia

.

.

.

Calidus Resources Warrawoona Gold Mine achieves record production rates in February – Daily production climbs to 180ozs per day

.

.

Calidus Resources (ASX:CAI) is pleased to provide an update on operations at its Warrawoona Gold Project (WGP) in February 2023.

.

Production Update

A total of 182,000 tonnes of ore at a reconciled grade of 0.89 g/t was processed with 5,005 ounces of gold recovered.

This equates to 180 ounces per day or 66,000 ounces annualised.

February numbers should be taken in the context of it being a short 28-day month and included a planned one-day mill maintenance shutdown.

During the month of February, mining achieved budgeted movement of 455,000 BCMs and the mill operated at 300tph, which is 6% above estimated blend throughput rate (factoring into account the amount of fresh ore being fed that has a budget throughput rate of 250tph).

.

.

Exploration Update

Drilling of 17 closely spaced holes targeting extensions of the previously reported high grade intercept of 6m @ 40.15 g/t Au at the newly discovered Felix deposit has been completed.

Assays are expected in early April.

.

.
Corporate Guidance for H1 CY 2023 remains unchanged at 31,000 to 36,000 ounces at A$2,000 to A$2,250 per ounce due to current maximum strip ratios being undertaken in the pit.

As the strip ratio decreases to LOM averages combined with the increased milling performance, the Company is targeting an average LOM Open Pit AISC of between A$1,700 to A$1,850 per ounce.

More detail will be provided in the guidance to be released at year-end.

The Company made a further A$5 million debt repayment in February reducing the outstanding balance of the Project Loan Facilities to A$97 million.

.

To read the full news release, please click HERE

.

=======

.

City Investors Circle is based in the financial district in the City of London

We present interesting and exciting junior mining companies listed on the ASX and TSX stock exchanges to a group of city professionals, and private investors, all of whom are active investors with a mandate to invest in junior mining companies.

Our audience is selected and invited individually to ensure interest and relevance for the presenting company.

Meetings are non deal, small group, highly focused and engaged, with a lively Q and A to follow the main presentation.

We create awareness, and maintain interest in presenting companies by disseminating their future news to our entire investor group via email, social media, and our Monthly Review newsletter.

If you wish to present to our select group of active mining investors, please email andrew@city-investors-circle.com

.

=======

,

This website is not sponsored, we are truly independent, and will always remain so.

Companies featured here have either presented to the Circle in London, or have been selected because they are considered to have interesting projects, in good jurisdictions, run by an experienced management team.

All information used in the preparation of this communication has been compiled from publicly available sources that we believe to be accurate and reliable, however, we cannot, and do not, guarantee the accuracy or completeness of this.

These articles are for awareness and informational purposes only, and are not recommendations in any form.  Always consult an investment professional.

.

.

Disclosure

At the time of writing the he author holds shares in Calidus Resources.

.

.