Cornish Metals South Crofty Progress Report

Cornish Metals (TSX-V/  AIM: CUSN)

Provided an update on progress at the South Crofty Tin Project , located in Cornwall, SW England.

 

.

Cornish Metals South Crofty sunset

Cornish-metals-south-crofty-sunset-Greg-Martin-Cornwall-Live

 

.

Cornish Metals TSX.V : CUSN
Stage Exploration
Metals Tin, copper
Market cap C$122 m   @ 23c
Location Cornwall, United Kingdom

 

.

 

Cornish Metals Provides South Crofty Tin Project Progress Report


 

Targeting water treatment plant commissioning and start of mine dewatering this summer – Pump Installation to commence this month

 

.
Cornish Metals Inc.(TSX-V/AIM: CUSN) (“Cornish Metals” or the “Company”) is pleased to provide an update on progress at the South Crofty Tin Project (“South Crofty” or the “Project”), located in Cornwall, SW England.

.

.

Richard Williams, CEO and Director, stated

“The team in Cornwall has made great progress over the last five months, despite adverse weather conditions.

 

“It is exciting to see the water treatment plant approach completion and we now start turning our attention to the commissioning and commencement of mine dewatering activities this summer.

 

“Further news on the metallurgical drill and testwork programme and ongoing Feasibility Study will be issued shortly.”

.

 

Mine Water Treatment Plant

The mine water treatment plant (“MWTP”) is designed to treat 25,000 cubic metres (“m3”) of mine water per day, and based on historic pumping records, mine dewatering is estimated to take 18 months to complete. Photographs of the construction of the MWTP can be viewed below, and progress on the MWTP is summarised below:

  • All tanks, except the CO2 and deep cone thickener, have been installed with those remaining items expected to be in place by the end of May.
  • All structural steelwork and walkways around the tanks have been assembled and the pipework connecting the tanks and tank valve installation is underway. The MCC (Motor Control Centre) design is complete and manufacturing underway with delivery expected in June.
  • Wet commissioning of the MWTP is now expected to commence in late June (rather than late May) and extend through July, with commencement of mine dewatering in early August.
  • The discharge pipes from the MWTP down into the Dolcoath Deep Adit (the historic drainage tunnel running northwards from South Crofty beneath Pool and Camborne to Roscroggan) have been installed.  A turbine will be added ahead of the discharge point that will generate up to 15% of the electricity required to operate the MWTP.
  • The first submersible pump has been successfully tested offsite and is now ready for imminent installation into New Cook’s Kitchen (“NCK”) shaft. The second pump is to be delivered by the end of May for subsequent installation. Piping from NCK shaft to the MWTP is substantially complete.
  • The building housing the high voltage power supply / sub-station and variable speed drives required to operate the pumps is complete, and the 11kV power supply is scheduled to be in place in June.
  • The cost of construction of the water treatment plant is forecast at £6.5 – £7.0 million.

 

Shaft Re-access Work

Progress on the NCK shaft re-access work is summarised below:

  • Two single drum winders have been ordered for the shaft re-access work, with the main winder from Siemag Tecberg and an emergency winder from Zitron. They are due on site in October and August this year respectively.
  • Conveyance and rope attachment packages for both winders are now being tendered for design and fabrication, and new winding ropes have been ordered for both machines.
  • Both sheave wheels and bearing blocks have been removed from the South headframe. The eastern sheave wheel has been split and the shafts and bearings are now ready for NDT (non-destructive test) testing.
  • Test runs of the submersible pump installation into the shaft have been successfully completed, and the pumps will be installed during May and June.
  • Interim shaft work platforms have been designed and are substantially fabricated. The above water timber compartments in the shaft have been inspected down to No.1 Level, with most sets found to be in good condition.

/

/

=======

.

If you need clarification of any information contained in this note, or have any questions, I will be delighted to assist – Please email andrew@city-investors-circle.com

=======

.

City Investors Circle is based in the financial district in the City of London

We present interesting and exciting junior mining companies listed on the ASX and TSX stock exchanges to a group of city professionals, and private investors, all of whom are active investors with a mandate to invest in junior mining companies.

Our audience is selected and invited individually to ensure interest and relevance for the presenting company.

Meetings are non deal, small group, highly focused and engaged, with a lively Q and A to follow the main presentation.

We create awareness, and maintain interest in presenting companies by disseminating their future news to our entire investor group via email, social media, and our Monthly Review newsletter.

If you wish to present to our select group of active mining investors, please email andrew@city-investors-circle.com

.

=======

,

This website is not sponsored, we are truly independent, and will always remain so.

Companies featured here have either presented to the Circle in London, or have been selected because they are considered to have interesting projects, in good jurisdictions, run by an experienced management team.

All information used in the preparation of this communication has been compiled from publicly available sources that we believe to be accurate and reliable, however, we cannot, and do not, guarantee the accuracy or completeness of this.

These articles are for awareness and informational purposes only, and are not recommendations in any form.  Always consult an investment professional.

.

.

Disclosure

At the time of writing the author holds no shares in Cornish Metals

 

To read our full terms and conditions, please click HERE