Minera Alamos files Cerro de Oro PEA

Minera Alamos (TSX.V: MAI)

Filed the results of the independent preliminary economic assessment (PEA) titled “NI43-101 Technical Report, Preliminary Economic Assessment and Mineral Resource Estimate for the Cerro de Oro Gold Project, Zacatecas, Mexico” on SEDAR. 

.

.

.

Minera Alamos

Minera Alamos three projects in Mexico

.

.

.

Minera Alamos TSX.v : MAI
Stage Development
Metals Gold
Market cap C$247 m   @ 54c
Location Sonora, Zacatecas, Durango – Mexico

.

.

.

Minera Alamos files Cerro de Oro PEA, technical report

2023-01-06 09:58 ET – News Release

Mr. Doug Ramshaw reports

MINERA ALAMOS FILES TECHNICAL REPORT AND PRELIMINARY ECONOMIC ASSESSMENT FOR THE CERRO DE ORO PROJECT

,

,

Minera Alamos Inc. (TSX.V: MAI) has filed the results of the independent preliminary economic assessment (PEA) titled “NI43-101 Technical Report, Preliminary Economic Assessment and Mineral Resource Estimate for the Cerro de Oro Gold Project, Zacatecas, Mexico” on SEDAR.

The results of the PEA were previously discussed in the company’s news release dated Oct. 3, 2022, highlights from which are included below. The report, effective as of Sept. 28, 2022, can be located under the Minera Alamos profile on SEDAR.

.

.

Highlights of PEA (all currency references are in U.S. dollars):

  • Production highlights:
    • Average annual gold production approaching 60,000 ounces (approximately 60,000 ounces to 70,000 ounces in years 1 through 4);
    • 8.2-year mine life based on initial minable total of 59 Mt (million tonnes) of mineralization (0.37 g/t (gram per tonne) gold) heap leached at an average rate of approximately 20,000 tpd (tonnes per day) — plus 0.4 g/t Au in years 1 through 4;
    • 477,000 ounces of gold produced in loaded carbon/dore;
    • LOM (life-of-mine) strip ratio of 0.3:1 (waste:mineralization);
  • Robust economics using a gold price of $1,600/ounce:
    • LOM all-in sustaining cost (AISC) of $873/ounce — averaging $763/ounce in years 1 through 4;
    • After-Tax NPV (net present value) at a 5-per-cent discount rate of $150.5-million and IRR (internal rate of return) of 111 per cent;
  • Low capital intensity project with rapid payback:
    • Preproduction capital costs of $28.1-million (includes 30 per cent contingency);
    • Payback period of 11 months;
    • Used crushing plant already purchased reduces up front capital requirements;
  • Significant upside:
    • Mineralization appears open in multiple directions, as well as to depth;
    • Additional metallurgical testing to examine amenability of gold recovery from deeper sulphide zones of mineralization not accounted for in current resource calculations and mine plans (some early indications that material may prove to be leachable);
  • Updated inferred mineral resource estimate containing 67 million tonnes of 0.37 g/t Au (790,000 ounces of contained gold) based on an upward revision of the base case resource gold price to $1,700/ounce.
.
.
.

.

.

=======

.If you need clarification of any information contained in this note, or have any questions, I will be delighted to assist – Please email andrew@city-investors-circle.com

=======

.

City Investors Circle is based in the financial district in the City of London

We present interesting and exciting junior mining companies listed on the ASX and TSX stock exchanges to a group of city professionals, and private investors, all of whom are active investors with a mandate to invest in junior mining companies.

Our audience is selected and invited individually to ensure interest and relevance for the presenting company.

Meetings are non deal, small group, highly focused and engaged, with a lively Q and A to follow the main presentation.

We create awareness, and maintain interest in presenting companies by disseminating their future news to our entire investor group via email, social media, and our Monthly Review newsletter.

If you wish to present to our select group of active mining investors, please email andrew@city-investors-circle.com

.

=======

,

This website is not sponsored, we are truly independent, and will always remain so.

Companies featured here have either presented to the Circle in London, or have been selected because they are considered to have interesting projects, in good jurisdictions, run by an experienced management team.

All information used in the preparation of this communication has been compiled from publicly available sources that we believe to be accurate and reliable, however, we cannot, and do not, guarantee the accuracy or completeness of this.

These articles are for awareness and informational purposes only, and are not recommendations in any form.  Always consult an investment professional.

.

.

Disclosure

At the time of writing the author holds shares in Minera Alamos.

.

.