Released the results of an engineering study on the hoisting capacity of the underground mining infrastructure on the Chimo mine property.

This property, owned 100 per cent by Cartier, is located 45 km east of Val d’Or. With simple adjustments, the shaft on the Chimo mine property could extract 1.7 million metric tonnes per year (4,921 metric tonnes per day).

.

.

.

Cartier Resources releases Chimo hoisting study results

2020-09-22 10:49 ET – News Release

Mr. Philippe Cloutier reports

CARTIER PRESENTS THE STRONG HOISTING CAPABILITIES OF THE SHAFT ON THE CHIMO MINE PROPERTY

.

Cartier Resources Inc. has released the results of an engineering study on the hoisting capacity of the underground mining infrastructure on the Chimo mine property. This property, owned 100 per cent by Cartier, is located 45 kilometres east of the Val d’Or mining camp.

.

Highlights:

  • With simple adjustments, the shaft on the Chimo mine property could extract 1.7 million metric tonnes per year (4,921 metric tonnes per day).
  • This study is one of four engineering studies carried out in tandem with a preparatory study for a new mineral resource estimate on the Chimo mine property to reveal its full value.

.

The study reveals that the components of the internal shaft structure could be used to hoist skips with a loading capacity of 20 metric tonnes each, travelling at a cruising speed of 2,200 feet per minute (40 kilometres per hour). This hoisting rate would raise 492 metric tonnes per hour of rock to the surface for a total of 4,921 metric tonnes per day in 10 hours of hoisting operations per 24-hour day, or 1.7 million metric tonnes year.

.

To date, two internal engineering studies have been completed with positive findings, including the study that is the subject of this press release. Two other internal engineering studies are still under way, as well as an internal preparatory study for a new mineral resource estimate, on the Chimo mine property.

.

No preliminary economic assessment, pre-feasibility study or feasibility study has been completed and disclosure of results from this internal study does not support or imply the technical feasibility and/or economic viability of the project. In addition, while current mineral resource estimates have been completed on separate zones on the property, mineral resources that are not mineral reserves do not have demonstrated economic viability.

.

An attached table shows the current and future features of the shaft infrastructure on the Chimo mine property.

.

About the Chimo mine project

Cartier holds a 100-per-cent interest in the property for which a 1-per-cent net smelter return royalty was granted to Iamgold Corp. No right of first refusal (buyback) was granted.

.

The most recent mineral resource estimate for the Chimo mine property, detailed in an attached table, uses a gold price of $1,300 (U.S.) per ounce and a cut-off grade of 2.5 grams per tonne gold.

.

Fourteen gold zones were mined by three producers between 1964 and 1997 for a production of 376,217 ounces of gold (MERN DV 85-05 to DV-97-01).

.

The mining infrastructure consists of a network of seven kilometres of drifts on 19 levels, connected by a shaft with a depth of 914 metres. The bridge and surface facilities were dismantled in 2008 but the 25-kilovolt power line and sandpit are still in place.

.

Cartier’s drilling programs to date on the Chimo mine property amount to 124 drill holes for 58,054 metres and 21,867 gold samples collected.

.

About Cartier Resources Inc.

Cartier Resources, founded in 2006, is based in Val d’Or, Que. The province of Quebec has consistently ranked as one of the best mining jurisdictions in the world, primarily because of its favourable geology, attractive fiscal environment and pro-mining government.

The company has a strong cash position with more than $13.9-million and significant corporate and institutional endorsements, including Agnico Eagle Mines, Meridian Global and Quebec investment funds.

Cartier’s strategy is to focus on gold projects with features that offer potential for rapid growth. The company holds a portfolio of exploration projects in the Abitibi greenstone belt of Quebec, one of the most prolific mining regions in the world.

The company is focused on advancing four key projects through drilling programs. These projects were acquired at reasonable costs in recent years and are drill ready, with targets along the geometric extensions of known gold deposits.

Exploration work is currently focused on the Chimo mine property to maximise value for investors. The company is also planning a major drilling program for the Benoist property. Drilling on the Fenton and Wilson properties will follow the Benoist program.

.

.

City Investors Circle is based in the financial district in the City of London.

We present interesting and exciting junior mining companies listed on the ASX and TSX stock exchanges to a group of city professionals, and private investors, all of whom are active investors with a mandate to invest in junior mining companies.

Our audience is selected and invited individually to ensure interest and  relevance for the presenting company.

Meetings are small group, highly focused and engaged, with a lively Q and A to follow the main presentation.

We create awareness, and maintain interest in presenting companies by disseminating their future news to our entire investor group via email, social media, and our Monthly Review newsletter..

If you wish to present to our select group of active mining investors, please email: andrew@city-investors-circle.com for information.

——-

This website is not sponsored.

We are truly independent, and will always remain so.

Companies featured here have either presented to the Circle in London, or have been selected because they are considered to have interesting projects, in good jurisdictions, run by an experienced management team.

These are not recommendations in any form.

Always consult an investment professional.